Lots to Report!

Progress has been going great at The Lake Club. Framing is coming to a close and the next phases are starting. The electricians have begun downstairs, the foundation crew is working to water proof and backfill the walls, and the … Continue reading

Posted in Hilton Head Lakes | Leave a comment

Progress at Hilton Head Lakes

Things are really coming along at the Lake Club. In the past two weeks we have been setting steel, framing walls, water proofing, and erecting trusses. Its been full steam ahead thanks to all of the great guys at PGA … Continue reading

Posted in Hilton Head Lakes | Leave a comment

Framing has kicked into high gear.

Framing has started with a fury! The first board was cut Friday at 3pm, its now 3pm on Monday and all of the lower level has been framed. Next to go up are the floor trusses. At the same time … Continue reading

Posted in Hilton Head Lakes | Leave a comment

Progress at Hilton Head Lakes

A lot of work has been done in the past week and a half. The perimeter wall has been formed, poured, and stripped. The columns at the lower level have been erected, and now we are starting to get the … Continue reading

Posted in Hilton Head Lakes | Tagged , , , | Leave a comment

P=(m+m)M

P=(m+m)M Progress equals Man power plus Material multiplied by Proper Management. If you can put the material on the job when it’s needed and get the boots on the ground to put it up, progress with the right guidance will … Continue reading

Posted in Hilton Head Lakes | Leave a comment

Lake club form work

If you blink you’ve fallen behind! Work is progressing at a very fast pace out here at the Lake Club. The first section of forms have been erected and are being squared and plumed today. At the same time the … Continue reading

Posted in Hilton Head Lakes | Leave a comment

Lake Club Time Lapse

Here is a brief time lapse movie and a recap up to date. Be sure and check back soon, things are moving fast!!  

Posted in Articles | 1 Comment

Work goes on…

The day after a milestone in a project always feels somewhat euphoric. After months and months of planning and anticipation the project starts, you mobilize, get the crews on site and put the shovels to the ground. You do layout, … Continue reading

Posted in Hilton Head Lakes | Tagged , | Leave a comment

We’ve Got Concrete!!

We’ve got Concrete! Today’s pour went about as smooth as you can get. Thanks to a great crew and concrete trucks lined up down the road we were able to pour 85 yards in under 3 hours.

Posted in Hilton Head Lakes | Tagged , | Leave a comment

First week!

What a great start! The perimeter footings have been dug and the steel is going in, and lots of it! Within the next week we will be doing compaction test, termite treatments, inspections and finally pouring our first batch of … Continue reading